SE Várzea Grande II

Substation · 230 / 138 kV · MT

SE Várzea Grande II

The company’s first Turn-Key project.

Contracts executed

  1. 2020

    Construction & build-out of the 230 and 138 kV sectors

    • 1x 230 kV line bay with line reactor
    • 230/138-13.8 kV transformer bank
    • 1x 138 kV line bay
    • 1x 138 kV ATF connection

Contact

Talk to Engetecnica