SE Padre Paraíso II

Substation · 500 kV · MG

SE Padre Paraíso II

3 different projects, including SVC implementation.

Contracts executed

  1. 2017

    Expansion under Lot 4 · Auction 013/2015

    • 1x 500 kV line bay
    • 1x 500 kV bus tie
    • 1x Line reactor bank (3x 90 MVAr)
  2. 2020

    Expansion under Lot 5 · Auction 013/2015

    • 500 kV Static Var Compensator (SVC) (-150/+300 MVAr)
  3. 2024

    Expansion under Lot 3 · Auction 013/2015

    • 1x 500 kV line bay
    • 1x Line reactor bank (3x 50 MVAr)