Substation · 500 / 230 kV · BA
SE Barreiras II
5 different projects in the same substation.
Contracts executed
- 2015
Expansion under Lot C1 · Auction 002/2013
- 1st 500/230 kV transformer bank (4x 100 MVA)
- 1x 500 kV bus tie
- 1x 500 kV line bay
- 1x 230 kV bus tie
- 2019
ATF bank reinforcement (ReA)
- 2nd 500/230 kV transformer bank (3x 150 MVA)
- 2022
Expansion
- 1x 230 kV three-phase reactor bay