Substation · 500 / 440 kV · SP
SE Assis
Two simultaneous contracts for TAESA at the same substation.
Contracts executed
- 2024
REA · 2nd 500/440 kV autotransformer bank (TAESA)
- BoP for the 2nd bank of single-phase 500/440 kV autotransformers (3x 500 MVA)
- Civil works, electromechanical erection and interconnections
- First use of 500 kV insulated cable in Brazil
- 2024
500 kV expansion · Lot 1 Ananaí · Auction 002/2021 (TAESA)
- Expansion of the 500 kV sector of SE Assis, with a new control house and integration into the existing installations